Project Overiew:

The project was located in Cairo of Egypt, which was an orchard with 1000 acre area. Raw water was Nile river water. Our Egypt client adopted our brackish desalination for irrigation to produce fresh water for meeting his orchard irrigation need. The production capacity was totally 480 tonnages per day(20 T/H).

Irrigation Desalination Plant Technological Process

Afsaltning til kunstvanding

Forberedelse før ibrugtagning

S.N Kontrol af genstande Krav Standard
1 Om der er foretaget en analyse af indløbsvand fra omvendt osmose. Resultatet af vandkvalitetsrapporten opfylder kravet til omvendt osmoseindløb.
2 Uanset om der findes kemikalier til idriftsættelse, idriftsættelsesværktøjer, analyseinstrumenter og målere. Ibrugtagningskemikalier opfylder designkravene, og værktøjer og analyseinstrumenter er klar.
3 The water, electricity and gas system of the process system has the ability of continuous supply, and whether the drainage ditch has the discharge conditions. Vand, elektricitet, gassystem har evnen til kontinuerlig forsyning. Afløbsgrøften har udledningsbetingelserne, dræningen er jævn og i overensstemmelse med designkravene.
4 Whether the water tanks related to the reverse osmosis have been cleaned, and cross-sectional area has been measured (feed water tank, concentrated tank and production tank). Der er ikke noget snavs i rentvandstankene, og tværsnitsarealet er blevet målt.
5 Kontrollér, om alle rør er tilsluttet fuldstændigt i henhold til designkravene, og om rørskåle er installeret solidt. Kontrollér, om alle rør er tilsluttet fuldstændigt i henhold til designkravene, og om rørskåle er installeret solidt. Opfylder kravene i designtegningerne, og skipperne er installeret solidt.
6 I henhold til PID skal du kontrollere, om mængden af alle rør, trykmåler, niveauafbryder, flowmåler, ledningsevnemåler og SDI-instrument er i overensstemmelse med designkravene. Overhold designkravene.
7 Om MCC- og PLC-styringssystemet kan forsynes med strøm. Opfylder designkravene og kan vise normale data.
8 Om alle ventiler kan betjenes normalt, og om ventilernes hastighed er blevet justeret eller ej. neumatic valve can normally on-off, the speed of the valve meets the technical process requirements.
9 Om procesrørledningerne er blevet tryktestet, ingen lækage. Opfylder designkrav, ingen lækage.

On-site Problems & Solutions

1. Pretreatment system: we were only responsible for the reverse osmosis system, excluding pretreatment. Due to the pretreatment was substandard, 6.67 SDI, which will cause membrane fouling too fast. In order to improve the pretreatment system, our technical engineer suggested increasing the filters to reduce the filtration flow from 35m/h to 8m/h, the effect was improved. And adding the alums to improve SDI as there was no PAC on site.

2. Membrane fouling: we have not previously designed pure water flushing in this system, so some pipelines were rebuilt to increase the daily fresh water flushing and reduce the fouling.

3. Water drain problem: the owner directly connected the concentrated pipes and backwash pipes of filters to water intake for saving pipelines, which resulted in water intake TDS and turbidity rising, and had an effect to RO operating. So we suggested they revise the pipelines by connecting concentrated pipes and backwash pipes to other discharges.

4. Ukvalificeret behandling af trykbeholderens forbindelsesdel kaldet "Grenade": Der er to slags løsninger på dette problem. Den første er at oparbejde Grenade, og den anden er at afkorte 2 cm længde af forbindelsesforseglingsdelen. Sidst vedtog vi den anden og løste problemet inden for en halv time.

Konklusion

Endelig afsluttede ingeniør Victor Zhang installationen og idriftsættelsen af dette projekt med succes inden for en halv måned? 2015/12/21-2016/1/5). Vores kunde brugte vores RO-system til brakvand til at rense Nilvand til ferskvand til kunstvanding, hvilket i høj grad kan spare vandingsvand og forlænge frugttræernes levetid. Samtidig var han meget tilfreds med vores service, og vi var glade for at få det!