Inviateci la vostra fonte d'acqua, la capacità richiesta, la posizione dell'imbarcazione o del progetto, la modalità di funzionamento preferita e i requisiti di installazione. KYsearo può preparare una proposta tecnica diretta alla fabbrica, una soluzione di desalinizzazione RO personalizzata e un'offerta B2B per il vostro progetto marino, offshore, insulare o di acqua salmastra.

Caso di studio in Egitto: Come il nostro ingegnere ha messo in funzione una desalinizzazione per l'irrigazione

Project Overiew:

The project was located in Cairo of Egypt, which was an orchard with 1000 acre area. Raw water was Nile river water. Our Egypt client adopted our brackish desalination for irrigation to produce fresh water for meeting his orchard irrigation need. The production capacity was totally 480 tonnages per day(20 T/H).

Messa in funzione di una desalinizzazione per irrigazione

Irrigation Desalination Plant Technological Process

desalination for irrigation

Preparation before commissioning

S.NChecking ItemsRequirement Standard
1Whether analysis of Reverse Osmosis inlet water has been done.The result of water quality report meets the requirement of reverse osmosis inlet.
2Whether commissioning chemicals, commissioning tools, analysis instruments, and meters are available.Commissioning chemicals meet the design requirements, and tools and analysis instruments have been ready.
3The water, electricity and gas system of the process system has the ability of continuous supply, and whether the drainage ditch has the discharge conditions.Water, electricity, gas system has the ability of continuous supply. Drainage ditch has the discharge conditions, drainage is smooth, and in line with the design requirements.
4Whether the water tanks related to the reverse osmosis have been cleaned, and cross-sectional area has been measured (feed water tank, concentrated tank and production tank).No debris in the clean water tanks, and cross-sectional area has been measured.
5Check whether all piping are connected completely based on design requirements, and whether piping skips are installed solid. Check whether all piping are connected completely based on design requirements, and whether piping skips are installed solid.Meet the requirements of design drawings, and skips installed solid.
6According to PID, check whether the quantities of all piping, pressure gauges, level switch, flow meter, conductivity meter, and SDI instrument are in line with design requirements.Comply with design requirements.
7Whether MCC and PLC control system can be powered.Meet the design requirements, able to show normal data.
8Whether all valves can be operated normally, and the speed of the valves has been adjusted or not.neumatic valve can normally on-off, the speed of the valve meets the technical process requirements.
9Whether process pipelines have been pressure test, no leakage.Meet design requirement, no leakage.

On-site Problems & Solutions

1. Pretreatment system: we were only responsible for the reverse osmosis system, excluding pretreatment. Due to the pretreatment was substandard, 6.67 SDI, which will cause membrane fouling too fast. In order to improve the pretreatment system, our technical engineer suggested increasing the filters to reduce the filtration flow from 35m/h to 8m/h, the effect was improved. And adding the alums to improve SDI as there was no PAC on site.

2. Membrane fouling: we have not previously designed pure water flushing in this system, so some pipelines were rebuilt to increase the daily fresh water flushing and reduce the fouling.

3. Water drain problem: the owner directly connected the concentrated pipes and backwash pipes of filters to water intake for saving pipelines, which resulted in water intake TDS and turbidity rising, and had an effect to RO operating. So we suggested they revise the pipelines by connecting concentrated pipes and backwash pipes to other discharges.

4. Unqualified processing of pressure vessel connecting part called “Grenade”: There are two kinds of solutions on this problem. First one is to reprocess Grenade, and the second one is to curtail 2cm length of connecting seal part. Last we adopted the second one, and solved the problem within half an hour.

Conclusione

Finally, the Engineer Victor Zhang completed the installation and commissioning of this project sucessfully within half a month?2015/12/21-2016/1/5). Our client adopted our brackish water RO system to purify Nile water into fresh water for irrigation, which can greatly save irrigation water and prolong lifespan of fruit trees. At the same time, he was very satisfied with our service and we were pleased to get that!

Modulo di contatto
Kangyang Seawater Desalination Equipment Co.,Ltd
Desalinizzazione dell'acqua salmastra
Sistemi a osmosi inversa per acqua di mare
Sistemi RO in container
Macchina per la desalinizzazione solare
Sistemi industriali di ultrafiltrazione UF
Apparecchiature industriali per l'addolcimento dell'acqua
Sistema di trattamento dell'acqua di alimentazione della caldaia
Trattamento dell'acqua RO EDI
Circa
Applicazioni
Progetti
Prodotti
Blog
Contatto
+86 189 9155 0318
No.4, Shijiaoju Street, Dukou Road, Xinzao Town, Panyu Dist, Guangzhou, Guangdong, 511436 Cina.
Copyright © 2026 Kangyang Seawater Desalination Equipment Co.,Ltd